Construction of Phase 1 park improvements will continue into fall 2026. Temporary closure zones continue. Please follow the posted signs.
Planned reopening timeline:
Trail from Fire Station 1 into the park: Open
Beaches 3-5 (Central Beach and North Beach): Open
Washroom pavilion: Open
Playground: Open
Beach volleyball courts: Open
Tennis and pickleball courts: October 2026
Temporary court markings are currently in place. Acrylic surface coating will be placed in June 2027 due to temperature requirements during installation.
Beach 2 (South Beach): October 2026
New park exit: October 2026
Substantial completion of Phase 1: Mid-November 2026
Construction timelines are subject to change due to factors such as weather, site conditions, contractor scheduling, and material availability.