The Town of Innisfil is completing road rehabilitation on 6th Line, from 5th Sideroad to 20th Sideroad, this summer. Work includes pulverization of the existing road, base stabilization, reshaping with granular materials, and topping with a new surface.
Construction schedule
The contractor is scheduled to mobilize on July 8, 2026. The overall project is expected to be completed within 6 weeks, weather permitting. Residents may experience temporary disruptions, including noise, dust, and construction-related activity, while crews are on site.
Road closures
Road closures will be implemented by road section as work moves along 6th Line:
- 5th Sideroad to 10th Sideroad: July 8 to July 15, 2026 (rescheduled from June 22-26)
- 10th Sideroad to Yonge Street: Closed as of July 13
- Yonge Street to 20th Sideroad: Closed as of July 16
Access will be maintained for local traffic only, waste collection, and emergency services. Detours will be set up using 4th Line, 5th Line, and 7th Line as needed for other motorists.


We appreciate your patience and cooperation while this important work is being completed.
For more information about the section of 6th Line from County Road 27 to 5th Sideroad, please go to our Road Paving page.