Upcoming Site Works
The Town has approved a Pre-Development Agreement with the developer which will
allow preliminary site
work to begin.
This preliminary work will start with tree-clearing on the site. Other preliminary work over the next two years will include grubbing and grading, marina basin excavation, golf course shaping and haul road construction.
A tentative schedule of site preparation works, broken down by year follows:
2010 / 2011:
- approved tree clearing operations (Stage 1 Complete, Stage 1B/1B2 commencing early November)
- installation of approved erosion/sediment control measures (February)
- grubbing and stumping operations of cleared areas (December)
2012:
- haul road construction
- stripping of golf course (Spring)
- excavation of marina and marina resort area (ongoing through 2013)
- hauling of excavated materials to golf course lands
- dewatering of existing marina basin
- preliminary site preparation of external trunk servicing route
2012 / 2013:
- golf course shaping, seeding
- fine grading and shaping of marina basin and islands
- installation of underground services
- installation of external trunk services
- installation of marina and resort features; ie. dock anchors, landscaping, boardwalk