Upcoming Site Works

The Town has approved a Pre-Development Agreement with the developer which will
allow preliminary site
work to begin.

This preliminary work will start with tree-clearing on the site. Other preliminary work over the next two years will include grubbing and grading, marina basin excavation, golf course shaping and haul road construction.

A tentative schedule of site preparation works, broken down by year follows:

2010 / 2011:

  • approved tree clearing operations (Stage 1 Complete, Stage 1B/1B2 commencing early November)
  • installation of approved erosion/sediment control measures (February)
  • grubbing and stumping operations of cleared areas (December)

2012:

  • haul road construction
  • stripping of golf course (Spring)
  • excavation of marina and marina resort area (ongoing through 2013)
  • hauling of excavated materials to golf course lands
  • dewatering of existing marina basin
  • preliminary site preparation of external trunk servicing route

2012 / 2013:

  • golf course shaping, seeding
  • fine grading and shaping of marina basin and islands
  • installation of underground services
  • installation of external trunk services
  • installation of marina and resort features; ie. dock anchors, landscaping, boardwalk